Continuing kinematics #4, beam IN, target OUT (0 deg)
At 17:00 switching 0 -> 270 deg
Run# Start/Stop Comments, events Left/Right/Total (cumulative)
-------------------------------------------------------------------------------
3167/31167 14:34/15:29 OK, not analysed by day shift, 293k/261k/2451k
3168/31168 15:29/16:21 OK, inherited from day shift, 277k/247k/2975k
16:21/16:54 Tg polarisation measurement: 45.6% (NMR), 46.2% (EPR)
16:54 Tg holding field rotated to 270 deg
3169/31169 16:54/16:57 Junk run to check raster
3170/31170 17:01/17:58 OK, but beam very unstable, 235k/217k/452k
3171/31171 18:00/18:53 OK, 251k/222k/925k
3172/31172 18:55/19:48 OK, 268k/238k/1431k
3173/31173 19:49/20:43 OK, 308k/277k/2016k
3174/31174 20:44/21:38 OK, 277k/248k/2541k
3175/31175 21:39/21:40 Junk
21:40/22:05 Tg polarisation measurement: 43.7% (NMR), 43.4% (EPR)
3176/31176 22:10/22:12 Junk run to check raster
3177/31177 22:13/23:07 OK
3178/31178 23:08/23:29 OK, but stopped for QE measurement
23:29/23:55 MCC performs QE measurement and restore RF trips
23:55 Beam is back, resume running
3179/31179 23:55/----> Passed on to night shift
-------------------------------------------------------------------------------