Main INDEX
Monthly INDEX
PREV
NEXT
User name LeRose
Log entry time 16:01:48 on September 7,2001
Entry number 73727
keyword=Shift Summary
Day shift: John LeRose, Nilange Liyanage, Yuan Xiao
8:10 MCC says they're taking beam for 30 minutes to recover RF
8:16 Beam off
took the oportunity for a target polarization measurement (see halog#73691)
8:56 Beam Back on (It was really 30 minutes!)
Program is production data taking
Left arm:
P0=2.27 @ 18.602 deg
Right arm:
P0=2.27 @ 18.603 deg
Ebeam=5727 (set energy) 1/2 wave plate out
Target 1/2 wave plate out
target spin 270 deg
10:55 MCC/Hall C started beam asymmetry tests
13:45 Hall C finishes beam asymmetry tests
15:00 stop for target polarization measurement followed by Moller measurement
run.................start/stop...good e's.....total (this shift)
3328/31328 7:15/8:13 149k/148k 297k
3329/31329 8:14/8:20 4k/4k 301k
3330/31330 8:57/9:53 147k/147k 595k
3331/31331 9:55/10:50 92k/93k 780k
3332/31332 10:52/11:47 133k/135k 1048k
3333/31333 11:48/12:44 144k/144k 1336k
3334/31334 12:45/13:41 141k/141k 1618k
3335/31335 13:43/14:39 153k/155k 1926k
3336/31336 14:40/15:00 46k/46k 2018k