9:00
Q2 and Q3 qudrapoles from both arm were recycled
Dipole magnets are ramping up
9:50-10:20 NMR/EPR
10:00 Left spectrometer ready
10:20 check beam spot with raster off, OTR and BeO target. OK
10:30 raster check, ok, moved to pol. He3 target, target field changed to 270 degree
10:40 right arm ready, start production runs 3429,31429