    9/12 swing shift
    Shift workers: J. P. Chen, P. Solvignon, D. Dutta.

    16:00 Production data for Kin5, beam/target=IN/270degree.
    19:45 MCC need to tune for Hall B, took beam away from us.
    19:50-20:30 NMR/EPR=42.9%/42.9%
    20:30-21:54 Resume data taking at Kin5, In/270 degree.
    21:54- MCC take beam away to tune for Hall B.
    22:35 resume data taking.
    24:00 Hand to next shift.

    Good e before the shift: 1.00 M
    Run# good e Grand total
    3434/31434 134k/138k 1.27M
    3435/31435 137k/140k 1.55M
    3436/31436 128k/133k 1.81M
    3437/31437 114k/117k 2.04M
    3438/31438 134k/140k 2.31M
    3439/31439 41k/42k 2.39M
    3440/31440 149k/154k 2.69M
    3441/31441 still running at the end of shift