1600 | 1700 | 1800 | 1900 | 2000 | 2100 | 2200 | 2300 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0 | 0 | 0 | 53 | 56 | 54 | 57 | 55 | 4.58333333333333 |
Beam Available but Not in Use | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Beam Not Available or Unacceptable | 0 | 0 | 1 | 7 | 4 | 6 | 3 | 5 | 1.41666666666667 |
Accelerator Con- figuration Chage | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 2 |
Experiment Ready | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 8 |
Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Unplanned Experiment Down | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Ac | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: First ~90 minutes was down for tour of hall (SURA board). Beam restoration plus additional injector tuning continued until 19:05 5 hours of perfect running (except for a few trips).
Data Entry by: J Arrington