Main INDEX
Monthly INDEX
PREV
NEXT
User name ISSAM QATTAN
Log entry time 16:06:20 on November10,2001
Entry number 76853
keyword=summary
Day Shift: Continuation of G- kinematics
Started shift with run 1966
08:48 Beamline display dissappeared. Lost communication with gateway.
08:53 MCC is working on the gateway software inorder to correct display problems.
10:02 Beamline display returned
10:19 Beamline display dissappeared again. Network communication lost.
10:20 Network communication restored. Beamline display returns
10:40 Performing current scan measurements lowered beam from 75uA to 5 uA. run 1976
11:01 Performing current scan increased beam to 10 uA. Run 1977
11:21 Performing current scan at 20 uA. Run 1978
11:40 Increased beam current to 30 uA. Run 1979
12:07 Finished current scan measurements. Increased beam back to 75 uA. Start with Run 1980.