User name Mattias
Log entry time 00:26:16 on November29,2001
Entry number 78242
keyword=Shift summary
Shift summary 11/28/01 16.00-00.00
M. Andersson, K. Fissum, W. Hinton
16.00 : Shift started, problems with left Q3. The other magnets are on their way. Mark and Scott are working at it.
~18.00 : Mark and Scott finished with everything. Now we are just waiting for the right dipole.
19.45 : Left Q1 tripped. Had to make access to the hall to reset the power supply.
20.40 : Inserted BeO target to make beam centering tests. Requested 5uA.
21.15 : Left Q2 tripped. Recovered by itself.
22.50 : Left Q1 and Q2 tripped. Had to access the hall to reset Q1 power supply. Discovered pool of water under left dipole.
00.00 : Shift ended without beam.