0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 58 | 56 | 56 | 57 | 1 | 50.3 | 1 | 14 | 6.855 |
Beam Available but Not in Use | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Beam Not Available or Unacceptable | 2 | 4 | 4 | 3 | 0 | 0.011666 | 0 | 46 | 0.994999333333333 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 9 | 0 | 0 | 0.15 |
Experiment Ready | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 7.33333333333333 |
Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0.666666666666667 |
Unplanned Experiment Down | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Ac | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: 05:20 Daily q.e. measurement (9 min.) 07:15 Experiment 99-114 is complete. It was a good run. DVCS now has the Hall.
Data Entry by: Roedelbronn