• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 00:14:41 on May 23, 2002

    Entry number 4015

    keyword=Beam Time Accounting
    Hall A

    5/22/2002 1600-2400
    Experiment #: e01001
    Shift Leader: M Jones
    Shift Workers: P. Mousieg, H. Ibrahim

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    52 56 60 30 0 0 0 0 3.3
    Beam Available
    but Not in Use
    8 4 0 0 0 0 0 0 0.2
    Beam Not Available
    or Unacceptable
    0 0 0 0 0 0 0 0 0
    Accelerator Con-
    figuration Chage
    0 0 0 30 1 1 1 1 4.5
    Experiment
    Ready
    52 60 60 30 30 60 60 60 6.86666666666667
    Planned Config-
    uration Change
    8 0 0 30 30 0 0 0 1.13333333333333
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: 4: 00 Doing dummy target 4:45 Switch to 12C pointing at 70uA 5:05 Switch to 4cm Lh2 5:45 during run 1784 fixed downstream beam v-to-f cables.

    Data Entry by: M Jones