    Log entry time 08:01:41 on October 5, 2002

    Entry number 87350

    keyword=Beam Time Accounting
    Hall A

    10/5/2002 0000-0800
    Experiment #: e00007
    Shift Leader: B. Moffit
    Shift Workers: R. Gilman, S. Choi

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0 0 0 0 0 0 0 0 0
    Beam Available
    but Not in Use
    0 60 60 15 0 0 0 0 2.25
    Beam Not Available
    or Unacceptable
    60 0 0 45 60 60 60 60 5.75
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    60 0 0 45 60 60 60 60 5.75
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    0 60 60 15 0 0 0 02.25
    Hall not
    ready reasons

    Comments: 1:20 Access to check position of target ladder. 2:29 Access to reset left and right Q1s 3:17 Pulsed beam sent 4:00 MCC: Trouble delivering Beam. Optics Expert Called 5:22 Pulsed beam sent to dump 7:05 MCC: Changes made at injector. Sending CW to Hall-A dump 7:28 MCC checking beam stability. Moved into empty target position

    Data Entry by: B. Moffit