• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name H. Ibrahim

    Log entry time 08:06:22 on October30,2002

    Entry number 89303

    keyword=Owl Shift Summary

    12:00 a.m. Owl shift takes over. Shift crew: E. Chudakov, P. Monaghan and H. Ibrahim

    12:15 a.m. MCC called and said that they need about one hour to replace a defective magnet power supply before they can send us any beam.

    12:55 a.m. MCC said they will send 5 uA beam to check the beam line.

    12:58 a.m. MCC said they are ready to send us 100 uA beam.

    01:00 a.m. Beam is back at 100 uA.

    01:25 a.m. MCC said that IOCHA1 is not responding and they will reboot it for us.

    01:30 a.m. Beam is back.

    05:30 a.m. Target IOC rebooted. We asked MCC to take the beam.

    05:45 a.m. Beam is back.

    ____________________________

    Continuing Q3D_f30r kinematics:

    Run # 2845 (Production, 492 k events)
    Run # 2846 (Production, 1 M events)
    Run # 2847 (Production, 1 M events)
    Run # 2848 (Production, 1 M events)
    Run # 2849 (Production, 1 M events)
    Run # 2850 (Production, 1 M events)
    Run # 2851 (Production, 376 k events. Target IOC rebooted)
    Run # 2852 (Production, 1 M events)
    Run # 2853 (Production, 1 M events)
    Run # 2854 (Production, in progress)