0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.0 | 20.2 | 47.1 | 51.2 | 27.9 | 30.2 | 48.7 | 43.0 | 4.47166666666667 |
Beam Available but Not in Use | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0 |
Beam Not Available or Unacceptable | 60 | 39.8 | 12.9 | 8.8 | 32.1 | 29.8 | 11.3 | 17 | 3.52833333333333 |
Accelerator Con- figuration Chage | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0 |
Experiment Ready | 60 | 60 | 50 | 60 | 60 | 60 | 60 | 60 | 7.83333333333333 |
Planned Config- uration Change | 0.0 | 0.0 | 10 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.166666666666667 |
Unplanned Experiment Down | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0 |
Hall not ready reasons |
Comments: Average current about 65 microAmps during this shift
Data Entry by: Z.-E. Meziani