Hall A Experiment #: e00007
11/9/2002 1600-2400
Shift Leader: Vina Punjabi
Shift Workers: Charles Perdrisat, Xiaodong Jiang
1600 | 1700 | 1800 | 1900 | 2000 | 2100 | 2200 | 2300 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.00 |
Beam Available but Not in Use | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.00 |
Beam Not Available or Unacceptable | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 8.00 |
Accelerator Con- figuration Chage | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.00 |
Experiment Ready | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 8.00 |
Planned Config- uration Change | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.00 |
Unplanned Experiment Down | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.00 |
Hall not ready reasons |
Comments: No beam in this shift due to vacuum problem in the accelerator.
Data Entry by: Vina Punjabi