    User name A. Deur

    Log entry time 00:03:00 on November13,2002

    Entry number 90000

    keyword=Shift Summary

    16:15 MCC called to let us know that they have a problem with the power supply of a dipole of in the Hall A arc. We were not getting any beam anyway.
    18:57. The magnet is back. MCC is sending pulse beam now for tuning.
    19:01 MCC starts ramping the beam to I=100 uA.
    After a few beam trips, the beam has been pretty stable at 100 uA.
    21:40 left lecroy HV went off -> stop run 3126
    21:43 HV back. Start run 3127