Hall A Experiment #: e01020
11/18/2002 0000-0800
Shift Leader: B. Wojtsekhowski
Shift Workers: B. Reitz, A. Shahinyan
0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.0 | 0.166666666667 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.17 |
Beam Available but Not in Use | 0.174444444444 | 0.666666666667 | 0.75 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 1.59 |
Beam Not Available or Unacceptable | 0.825277777778 | 0.167777777778 | 0.25 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 6.24 |
Accelerator Con- figuration Chage | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.00 |
Experiment Ready | 1.0 | 0.366666666667 | 0.25 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 6.62 |
Planned Config- uration Change | 0.0 | 0.633333333333 | 0.75 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 1.38 |
Unplanned Experiment Down | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.00 |
Hall not ready reasons |
Comments:
Data Entry by: Bogdan W