    Log entry time 20:59:42 on January 8,2003

    Entry number 91058

    keyword=Beam Thru Compton Chicane

    Beam has been put through the Compton Chicane.

    Alexandre will try during night shift to take 1GeV Compton data.

    Tune time was 9 min.
    Total time to from request until beam back was 48 min.

    (note: I went to MCC and the change went rather smoothly.
    Since only 1 of the 3 operators had ever put been thru the Chicane
    before, time was spend training the other operators how do it.)