    4:00 Started Shift in controlled access while MCC prepares the change from
    first to fourth pass.
    5:00 MCC ready, but we need to finish access. Checking the Moller and
    checking the transverse lasers.
    6:00-800 Start tuning up beam to the Hall.
    While checking the beam. Halls A and C take beam charge asym. data.
    After Hall C has set their asym. to zero we find a 200 ppm asym. We
    will now use the IA system at the injector to make this asym. even
    smaller.
    8:30 Beam ready for physics. The beam spot is 110 by 130 um (run#86).
    The raster is set for 2mm radius. (ask MCC also for 2mm)
    8:40 Target Polarization Measurements
    9:40 Start Moller Measurements continued until midnight.