• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 15:59:03 on January 22, 2003

    Entry number 93019

    keyword=Beam Time Accounting
    
    	
    Hall A

    01/22/03 0800-1600
    Experiment #: E01-012
    Shift Leader: J. LeRose
    Shift Workers: R. Michaels, B. Moffit

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.380.580.070.000.000.000.000.001.03
    Beam Available
    but Not in Use
    0.040.030.000.000.000.000.000.000.07
    Beam Not Available
    or Unacceptable
    0.580.380.931.001.001.001.001.006.90
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: Made some progress on kinematics 5.2, then at 10:00 MCC did beam tests, and never recovered.

    Data Entry by: R. Michaels