    Log entry time 00:01:47 on January 26, 2003

    Entry number 93362

    keyword=Beam Time Accounting
    
    	
    Hall A

    01/25/03 1600-2400
    Experiment #: E01-012
    Shift Leader: ent
    Shift Workers: deur, solvignon

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.000.160.000.360.930.920.940.683.98
    Beam Available
    but Not in Use
    0.000.000.910.500.020.000.020.201.64
    Beam Not Available
    or Unacceptable
    1.000.850.090.140.050.080.030.122.38
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.000.757.75
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.250.25
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: BPM problems in A-Line; 6 pm waiting for troublesome beam steering; 7:33 pm after polarization measurement and carbon run back to 3He program; 11pm DAQ problems to change to unbuffered

    Data Entry by: ent