• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name jpchen

    Log entry time 16:16:14 on February 7,2003

    Entry number 95178

    keyword=Day shift 2nd half summary

    day shift summary (continues):

    11:15- 13:15 Beam study and hall a controlled access.
    controlled access ended at ~14:50. Bodo did the DAQ work needed for the GEn
    study. Vince and JP replaced the target oven RTD and switched EPR fibers.
    14:50 get back to beam permit and waiting for beam.
    Once beam comes, Moller will be performed.
    15:45 beam back, wrong wien angle (old 5 pass setting).
    Asked for Wien angle change to be optimal.
    At the end of the shift, Beam not back yet.