• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 08:20:34 on April 22, 2003

    Entry number 97987

    keyword=Beam Time Accounting
    
    	
    Hall A

    04/22/03 0000-0800
    Experiment #: E97-110
    Shift Leader: A .Camsonne
    Shift Workers: P. Solvignon

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Not Available
    or Unacceptable
    1.001.001.001.001.001.001.001.008.00
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: Beam not delivered in Hall A the last hour because of BCM reading problem

    Data Entry by: A. Camsonne