    Log entry time 16:00:53 on July 23, 2003

    Entry number 106342

    keyword=Beam Time Accounting
    
    	
    Hall A

    07/23/03 0800-1600
    Experiment #: E97-110
    Shift Leader: J. P. Chen
    Shift Workers: T. Holmstrom, B. Ma

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    1.001.000.000.000.000.000.000.002.00
    Beam Not Available
    or Unacceptable
    0.000.000.000.000.000.000.000.000.00
    Accelerator Con-
    figuration Change
    0.000.001.001.001.001.001.001.006.00
    Experiment
    Ready
    0.000.001.001.001.001.001.001.006.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    1.001.000.000.000.000.000.000.002.00
    Hall not
    ready reasons
    Target1.001.000.000.000.000.000.000.002.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments:

    Data Entry by: T. Holmstrom