Hall A Experiment #: E97-110
07/31/03 0800-1600
Shift Leader: ron gilman
Shift Workers: tim holmstrom, ramesh subedi
0800 | 0900 | 1000 | 1100 | 1200 | 1300 | 1400 | 1500 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Beam Available but Not in Use | 0.00 | 0.01 | 0.03 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.03 |
Beam Not Available or Unacceptable | 0.08 | 0.25 | 0.97 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 6.30 |
Accelerator Con- figuration Change | 0.92 | 0.73 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1.65 |
Experiment Ready | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 8.00 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Unplanned Experiment Down | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: Beam shows up just before 10. Aside from beam studies, 10-noon, spend shift trying to get good spot.
Data Entry by: Ron Gilman