    User name gilman

    Log entry time 16:01:10 on August 1,2003

    Entry number 108524

    keyword=day shift summary, August 1


    Day shift summary for 31 July 2003



    owl shift had just started kin 7.02 elastic scattering:
    2.84 GeV, BHWP out, THWP out, 0 degrees

    ~9:10 Kent does pita measurement so we can get beam
    charge asymmetry down to about 0.

    ~09:20 David puts in Compton detector as background
    conditions are now small; he miscommunicates with
    MCC and asks for beam off, but does not ask to mask
    detector motion. Trip.

    ~9:30 right arm ts0 problem. reset within coda appears to work.

    10:00 speak with Hall B about our BHWP plans

    10:15 start configuration change to ref cell, also put BHWP in
    so Kent can do charge asym fixes

    11:10 Kent has finished!

    11:22 going back to elastic scattering:
    New setpoints for charge asymmetry input from Kent's analysis.
    Target changed with target half wave plate in, rotate the holding field
    from 0 to 180. Beam half wave plate still in.

    11:51 target stable, ask for beam

    12:30 JP calls to ask about target configuration and whether
    it is depolarizing. Vince and Jaideep find a ``nonproblem'' (EPICS
    variables not updating) and a real problem, holding field got stuck
    at 90 degrees, did not go to 180 degrees.

    13:10 target pol 37 %, ask for beam back

    14:05 Seonho asks us to take data at 5 k to speed things up, we adjust ps1.

    14:41 ask mcc to take out bhwp

    15:55 start setting up spectrometer for next kinemtics