    User name jpchen

    Log entry time 15:06:16 on August 7,2003

    Entry number 109284

    keyword=MD work completed in Hall A, sweep in progress

    All maintenance work completed:
    Hall Techs completed MD work and had the checklist done.
    Vince did quick mapping of Septum field at the taregt region for Septum
    setting of 300A, 350 A and 400 A, then turned on the compensating coils
    for Septum at 400 A, did a mapping. Then a training of Septum to 429.2 A.
    The hall is currently being sweeped to go into beam permit.

    Hall is sweeping