    Log entry time 01:02:44 on August 9,2003

    Entry number 109444

    keyword=Thick sieve removed, target collimators installed, ice removed.

    Took an controlled access: removed the thick sieve, inserted the thin sieve slits to
    adjust the collimator around the sieve. Then removed the thin sieve slits.
    Installed the 9 degree target collimators. Ready for production.
    Checked the ice, there was a thin layer at the bottom 1/4 of the acceptance. Removed
    it. Will need to check again when there is an access next time.