Log entry time 06:57:16 on August13,2003
Entry number 110506
keyword=vacuum problem update
MCC have just told us that they believe the vacuum problem has been caused by bleedthrough into the hall B beamline, while hall B was in controlled access.
They are awaiting the vacuum experts to arrive and investigate the problem. Unfortunately, they do not believe we will have any beam before the scheduled energy change this morning. This is disappointing as we are close to finishing the kinematic point 8.26 - about 30 minutes from finishing it.