Hall A Experiment #: E97-110
08/17/03 0000-0800
Shift Leader: J. Singh
Shift Workers: J. Cornejo, B. Moffit
0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.33 | 0.00 | 0.00 | 0.22 | 0.32 | 0.17 | 0.08 | 0.38 | 1.50 |
Beam Available but Not in Use | 0.00 | 0.00 | 0.00 | 0.70 | 0.57 | 0.77 | 0.92 | 0.62 | 3.56 |
Beam Not Available or Unacceptable | 0.67 | 1.00 | 1.00 | 0.08 | 0.12 | 0.07 | 0.00 | 0.00 | 2.94 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 1.00 | 1.00 | 1.00 | 0.30 | 0.43 | 0.23 | 0.08 | 0.38 | 4.43 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.70 | 0.57 | 0.77 | 0.92 | 0.62 | 3.57 |
Unplanned Experiment Down | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: 0000:0120 recovering from Moller 0120:0325 checking spotsize, raster, and beam position 0545:0635 controlled access: removed sieve slit
Data Entry by: J. Singh