Log entry time 14:51:57 on August21,2003
Entry number 112421
keyword=Target Collimators removed
After I finished fixing the EPR system, I removed the target collimators in preparation for acceptance studies at 4.4 GeV. I also did a quick check for ice on the Septum entrance window. I looked from the scattering chamber and I could see through the sieve collimator opening back to the Septum entrance. I could clearly see the green foam and I did not see any ice, but I could not see the lower 1" of the foam.