    Log entry time 16:04:50 on August 21, 2003

    Entry number 112436

    keyword=Beam Time Accounting
    
    	
    Hall A

    08/21/03 0800-1600
    Experiment #: E97-110
    Shift Leader: D. Higinbotham
    Shift Workers: R. Roche, Y. Qiang

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.370.000.000.000.000.010.670.601.64
    Beam Available
    but Not in Use
    0.250.000.000.000.000.490.170.070.97
    Beam Not Available
    or Unacceptable
    0.230.000.000.000.140.110.170.000.64
    Accelerator Con-
    figuration Change
    0.171.001.001.000.860.390.000.334.76
    Experiment
    Ready
    0.751.001.001.001.001.000.831.007.58
    Planned Config-
    uration Change
    0.250.000.000.000.000.000.170.000.42
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: Finished kinematics 10.20 with reduced stat. At 8:50 RadCon test of ion chambers began After RadCon test, pass was changed 2->4 And we did current calibration and septum heating test.

    Data Entry by: Higinbotham