• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name jpchen

    Log entry time 13:28:04 on August25,2003

    Entry number 113457

    keyword=pass chaneg, beam tuning for the A line. 3 pm is estiamated time

    MCC had some problems earlier. They finally put us back to beam permit around noon time. Now they are ready to send pule beam to tune the Hall A line. I asked for an estimate of when the pass change will be completed so that we can have a controlled access (to fix the right arm dipole problem). The estimation is 3 pm (might be earlier).