User name J. Singh
Log entry time 08:08:03 on August29,2003
Entry number 114202
keyword=owl shift summary
owl shift run summary
Last night since 1800 (swing shift), we have had no beam. Once we got it back we spent about 30 min doing the standed harp/otr/raster checks. In addition they took beam away for about 45 min to restore beam to hall C. After that it was smooth sailing. Apparently [(leftover cake) + MCC = ABU).
0000:0200 waiting for beam & getting tune beam periodically
0200:0348 harp, otr, beam gone to fix up hall C & then finish harp/otr
0348:0401 kin 11.16, carbon multifoil, raster OFF / OUT, y_tg spectra
0401:0407 moving to ref cell
0407:0413 kin 11.16, ref cell = empty / OUT
0413:0416 fill with N2, 140/141 psig
0416:0427 kin 11.16, ref cell = N2 / OUT
0427:0451 move to pol 3He, NMR = 42.5%
0451:0505 kin 11.16, Pol 3He, 0 deg / OUT
0505:0507 BHWP = IN
0507:0524 kin 11.16, Pol 3He, 0 deg / IN
0524:0537 rotate to 0 deg
0537:0548 kin 11.16, Pol 3He, 270 deg / IN
0548:0617 changing to kin 11.17, rotate to 0 deg, move to ref cell, giving MCC the cake leftover from the end of run party
0617:0625 kin 11.17, ref cell = empty / IN
0625:0628 filling with 139/140 psig N2
0628:0632 kin 11.17, ref cell = N2 / IN
0632:0641 move to Pol 3He
0641:0655 kin 11.17, Pol 3He, 0 deg / IN
0655:0656 BHWP = OUT
0656:0710 kin 11.17, Pol 3He, 0 deg / OUT
0710:0721 rotate to 270 deg
0721:0730 kin 11.17, Pol 3He, 270 deg / OUT
0730:0757 changing to kin 11.18, rotate to 0 deg, move to ref cell
0757:0802 kin 11.18, ref cell = empty / OUT