    Log entry time 16:00:49 on December 21, 2003

    Entry number 114901

    keyword=Beam Time Accounting
    
    	
    Hall A

    12/21/03 0800-1600
    Experiment #: Commission
    Shift Leader: Bogdan W.
    Shift Workers: Ryan Snyder, Bodo Reitz

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.540.170.000.000.000.000.000.441.16
    Beam Available
    but Not in Use
    0.290.490.900.960.940.970.980.435.95
    Beam Not Available
    or Unacceptable
    0.170.330.100.040.060.030.020.130.88
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.670.170.000.000.000.000.000.581.42
    Planned Config-
    uration Change
    0.330.830.000.000.000.000.000.001.17
    Unplanned
    Experiment Down
    0.000.001.001.001.001.001.000.425.42
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.001.001.001.001.001.000.425.42
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: a long cool down for the septum is the reason for the experiment not being ready over 5 hours.

    Data Entry by: R. Snyder