Hall A Experiment #: Commission
12/21/03 1600-2400
Shift Leader: Markowitz
Shift Workers: Ambrozewicz, Reitz
1600 | 1700 | 1800 | 1900 | 2000 | 2100 | 2200 | 2300 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.95 | 0.97 | 0.83 | 0.92 | 0.95 | 0.91 | 0.81 | 0.65 | 6.98 |
Beam Available but Not in Use | 0.00 | 0.00 | 0.06 | 0.00 | 0.00 | 0.06 | 0.05 | 0.00 | 0.17 |
Beam Not Available or Unacceptable | 0.05 | 0.03 | 0.12 | 0.08 | 0.05 | 0.03 | 0.14 | 0.35 | 0.85 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 0.95 | 0.97 | 0.83 | 0.92 | 0.95 | 0.90 | 0.82 | 1.00 | 7.33 |
Planned Config- uration Change | 0.00 | 0.00 | 0.07 | 0.00 | 0.05 | 0.05 | 0.13 | 0.00 | 0.30 |
Unplanned Experiment Down | 0.05 | 0.03 | 0.12 | 0.08 | 0.00 | 0.03 | 0.05 | 0.00 | 0.37 |
Hall not ready reasons | |||||||||
Target | 0.05 | 0.03 | 0.12 | 0.08 | 0.00 | 0.00 | 0.00 | 0.00 | 0.28 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.03 | 0.05 | 0.00 | 0.08 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: Target H2O calibration
Data Entry by: Markowitz