Hall A Experiment #: E94-107
01/23/04 0000-0800
Shift Leader: R. Feuerbach
Shift Workers: S. Marrone
0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.74 | 0.89 | 0.83 | 0.33 | 0.80 | 0.62 | 0.60 | 0.87 | 5.67 |
Beam Available but Not in Use | 0.03 | 0.05 | 0.10 | 0.45 | 0.10 | 0.15 | 0.27 | 0.10 | 1.26 |
Beam Not Available or Unacceptable | 0.22 | 0.07 | 0.06 | 0.22 | 0.10 | 0.23 | 0.13 | 0.03 | 1.06 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 1.00 | 1.00 | 1.00 | 0.50 | 1.00 | 0.83 | 0.75 | 1.00 | 7.08 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.33 | 0.00 | 0.00 | 0.00 | 0.00 | 0.33 |
Unplanned Experiment Down | 0.00 | 0.00 | 0.00 | 0.17 | 0.00 | 0.17 | 0.25 | 0.00 | 0.58 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.17 | 0.00 | 0.17 | 0.25 | 0.00 | 0.58 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: BNA from 3-4am was largely spent finding the work-around to get a small raster-size for the waterfall target. Trips of the RICH detector were the reason the experiment was not ready.
Data Entry by: R. Feuerbach