    Log entry time 12:48:20 on April 16, 2004

    Entry number 118063

    keyword=Beam Time Accounting
    
    	
    Hall A

    04/16/04 0000-0800
    Experiment #: E94-107
    Shift Leader: J. Singh
    Shift Workers: R. Feuerbach

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.000.000.000.330.380.330.400.311.75
    Beam Available
    but Not in Use
    0.000.750.000.170.000.000.000.541.46
    Beam Not Available
    or Unacceptable
    1.000.251.000.500.620.670.600.154.78
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.000.001.001.001.001.001.001.007.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.001.000.000.000.000.000.000.001.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.001.000.000.000.000.000.000.001.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: Beam tuning, and harp readout problems (until 3:45 am).

    Data Entry by: R. Feuerbach