• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 01:50:36 on April 17, 2004

    Entry number 118199

    keyword=Beam Time Accounting
    
    	
    Hall A

    04/16/04 1600-2400
    Experiment #: E94-107
    Shift Leader: F. Garibaldi
    Shift Workers: D. Margaziotis, R. Snyder

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.280.000.240.430.590.150.000.101.80
    Beam Available
    but Not in Use
    0.450.900.710.520.360.310.040.193.49
    Beam Not Available
    or Unacceptable
    0.270.100.050.040.050.540.960.702.71
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.000.001.001.001.001.001.001.007.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.001.000.000.000.000.000.000.001.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.001.000.000.000.000.000.000.001.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: ~1700:1800 controlled access to fix VDC

    Data Entry by: F. Garibaldi