    User name X. Zheng

    Log entry time 00:02:57 on May13,2004

    Entry number 121541

    keyword=May 12 swing shift summary

    16:00 shift start with controlled access;
    17:00 hall is in beam permit;
    18:10 beam back, start from 5 uA. Trying to figure out how to start the dump viewer;
    18:30 MCC asked to move the target to empty position for some tests,
    but the target IOC seems to be frozen, reboot target IOC;
    18:36 target in empty position; MCC is tuning the beam and trying to calibrate the beam dump viewer; For dump viewer calibration, see ELOG #1211800


    17:53 MSS is almost ready to send high current, move the target to Be thick (as labelled, the actual target is Be thin)

    20:16 we've got 120uA! Energy spread high (3.5E-5);
    20:20 start production runs;
    21:00 energy spread below 3.0E-5 now;
    23:00 MCC started QE test, beam down for about 8 minutes;



    run summary:

    run#   start   stop   #event   comment

    3482   20:15   20:38   1M     energy spread \approx (3.5-3.6)E-5

    3483   20:39   21:10   1M     energy spread drops from 3.5E-5 to 3.0E-5

    3484   21:11   21:40   1M

    3485   21:41   22:10   1M

    3486   22:11   22:27   72K    lost beam at the middle of run

    3487   22:44   23:18   1M

    3488   23:22   23:49   1M

    3489   23:52