     E04-012 Shift Plan: Saturday, May 22, 8:00 am - Sunday, May 23, 12:00 am

    May 22, 9:00 am, Olivier Gayou, Run Coordinator (pager 584-5411)

    Program: 

    Beamline check run plan

         LEFT:    p0 = 2.490 GeV/c    (+ polarity)         RIGHT:    p0 = 2.500 GeV/c     (- polarity)

                        septum:  0.0 A                                                        septum:  0.0 

    Move to BeO target, and ask for 5muA, centered on (O,O) on BPM A and B (+/- 0.1), raster OFF: check beam on viewer: beam should be centered on the camera. MCC should be able to see the beam on the dump viewer.

        LEFT Septum: 230.52 A     (+polarity)         RIGHT Septum: 231.45 A      (- polarity)
    Neutron kinematics run plan
            - ps7 = 1;
            - ps6 = 65535;
            - T1  =  T3  =  75 Hz;
            - T2  =  T4  =  T1 / 10  =  T3 / 10;
            - T5 so that TOTAL acquisition rate is 700 Hz ( = T1 + T2 + T3 + T4 + T5 + T7)
           -  beam position: (check the white board)
           -  Watch the SLI to monitor energy spread. We want energy spread < 6e-5.
                            25 muA, GOAL -> 3 hours ABU

                            50 muA, GOAL -> 3 hours ABU

    Scheduled events/Special tasks:

    General Tasks:

    Known Problems

    Please log below (and in the HALOG) any unusual observations and problems solved
    Date/Time Name Comment HALOG