    Log entry time 00:00:59 on May 29, 2004

    Entry number 123641

    keyword=Beam Time Accounting
    
    	
    Hall A

    05/28/04 1600-2400
    Experiment #: E04-012
    Shift Leader: J. Arrington
    Shift Workers: V. Nelubin, T. Holmstrom, C. Munoz Camacho

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.910.910.730.790.870.930.580.776.49
    Beam Available
    but Not in Use
    0.080.070.090.070.110.060.410.141.03
    Beam Not Available
    or Unacceptable
    0.010.040.180.130.030.020.020.080.51
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.000.631.007.63
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.370.000.37
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.370.000.37
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: 22:30 lost 20 min to DAQ recovery lots of data on Kin 10, smooth, steady beam