    No beam for the entire shift.
    Got all magnets up (Right Dipole gave less trouble than expected)
    All Q2's and Q3's were cycled.
    Went to controlled access.
    Left Dipole tripped (Low Helium). Helium level came back on its own. was able to restart power supply after all interlocks cleared.
    Went to power permit.
    Went back to controlled access for some short detector work.
    Left dipole tripped again. Same as before. Came back after interlocks cleared.
    Informed MCC they could go back to power permit whenever they were ready.
    Left dipole is back at the end of the shift.