    User name adaq

    Log entry time 16:09:59 on June 9, 2004

    Entry number 125188

    keyword=Beam Time Accounting
    
    	
    Hall A

    06/09/04 0800-1600
    Experiment #: E00-114
    Shift Leader: Higinbotham
    Shift Workers: Chen, Kelleher

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.550.670.710.620.590.400.140.003.68
    Beam Available
    but Not in Use
    0.420.240.260.210.260.410.310.002.12
    Beam Not Available
    or Unacceptable
    0.030.100.030.160.150.180.551.002.19
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    0.580.770.700.780.730.580.000.004.15
    Planned Config-
    uration Change
    0.420.230.270.220.270.421.001.003.82
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: Finished Optics and Bullseye Scan At 2:30 Hall went to controlled access to change the target and remove the sieve.

    Data Entry by: Higinbotham