    User name Z.-E. Meziani

    Log entry time 00:02:34 on June11,2004

    Entry number 125296

    keyword=Shift summary

    Swing shift
    16:00 Beam is in hands of MCC for beam studies.
    19:40 Q1 tripped. He level recovered. Couldn't power on by remote.
    20:01 Tech on call contacted. Planned access after beam studies completed.
    20:50 Access to the Hall for gate timing adjustments on the right parity detector. Tech on call not here yet.
    21:05 Tech accessed the Hall to reset Q1 left.
    21:20 Q1 reset and ramping back to 1820 Amps. Tech on call left.
    22:00 Everyone out of Hall. Requested beam back.
    22:00 Target Be0, raster on with 1 uA beam. Checked centering and spot size. Looks good.

    22:20 Moving target to He4 position
    22:25 Asked for 1 uA
    No triggers on the left Happex detector

    23:00 VDC high voltages on the right arm to 4 KV.
    Reducing the beam current to 0.5uA
    Testing of the alignment of the right Happex detector (R. Michaels)
    23:20 Finished the alignment test on the right Happex detector
    VDC back to 0 KV. All high voltages off except for the Happex
    detectors.
    23:50 Starting the increased current tests on septa behaviors

    24:00 Swing shift ends in the middle of the tests.