User name aniol
Log entry time 23:59:34 on June14,2004
Entry number 125779
keyword=shift summary
15:55 prod run 2127 started
16:51 end run 2127, 100k trig
16:55 dithering run 2128 started
17:07 end run 2128, 20k trig
17:15 prod run 2129 started
18:10 end run 2129, 100k trig
18:11 prod run 2130 started
18:20 beam trip off
18:53 MCC will send 5uA to reestablish the beam
18:53 end run 2130 - most of the time the beam was off
18:54 prod run 2131 started at 28.3 uA
19:56 end r2131, septa had tripped off about 19:15
20:00 attempt tp restart septa - no luck
We called Heidi and she walked us through a reboot for the septa. This did not work - see separate entry - She is coming in.
20:50 Heidi and Brian go downstairs to reload the PLC software for the septa.
21:15 Q1 left tripped off - We went down to reset the ps.
21:30 septa control restored by Heidi
21:52 septa are ramping up SLOWLY
22:25 right septum is at 278.25A, left is at 242A and still rising. We decide to take data using the RHRS until the left septum gets to full current.
22:30 start run 2132, production, LHRS is junk
23:05 end run 2132, 67K good trig for RHRS
23:18 tried dithering on r2133 and r2134 but the pan analysis gui is not responding correctly
23:24 end dithering run 2134 - restarted pan and saw dithering is ok
23:32 Lisa starts the PITA scans