    User name C. C. Chang

    Log entry time 16:03:55 on July 1,2004

    Entry number 127620

    keyword=Shift Summary

    Run#	Start	Stop	#Events	Comments
    2578	07:29	08:26	100 K	Good production run
    2579	08:27	09:23	100 K
    2580	09:25	09:46		Good run
    2581	09:47	10:43		Pedestal run
    2582	11:00	11:50	100 K
    2583	11:56	12:51	100 K
    2584	12:52	12:57		Very short production run
    
    
    Additional comments
    09:50	Request hall access
    10:05	All display screens respond slowly. Reboot hacsbc2.
    10:20	IHWP is in OUT position.
    10:42	Finish work down in the hall. Called MCC to give us beam as
            soon as it is available.
    12:47	Noticed beam tripped off often. Called MCC and was told that
    	it was caused by the vacuum trip in the injector.
    13:00	Stop production run and begin arc energy measurement.
    14:51	Rob requested to turn beam modulation off for now. Arun is 
    	still doing ARC energy measurement.
    15:40	Failed to carry arc energy measurement. Decided to scrapt
    	the measurement and will continue for production runs. 
    15:55	Restore production settings; beam spot size 3.5 by 3.2.