    User name Alex,J-M & Carlos

    Log entry time 07:56:18 on October 2,2004

    Entry number 132652

    keyword=Shift summary

    0:00 CODA still flaky
    2:20 MCC called they need to work on a power supply, if what they will
    try does not work, they might need to call somebody else so no beam for some time.

    03:30 Calorimeter LED run (new block positions). Run 2939.

    03:45 Called MCC to get an estimate : 3hours...

    04:33 Run cosmic (config not working)

    04:52 Pedestal run (DVCS config with calorimeter threshold=5,5, no beam). Run 2946.

    05:10 More detailed scan of calorimeter blocks 0,11,120 and 131 with LED (step size 1mm). Run 2947. Estimated time 95min.

    05:15 MCC called : ready to send beam. Stopped LED run and taking 2.5uA.

    05:25 Want to check beam. Called MCC to change the target to empty and do a harp scan.

    06:03 The beam doesn't look good yet. Putting BeO target to have a look.
    Looks ok.

    06:16 Back to empty target and redo harp scan. After several iterations with MCC, beam is now within the specifications (06:29). We asked for tuning position at BPM4B-y to 1.4 (was 1.2).

    06:35 Going back to 15cm-LH2 target.
    06:39 Taking back 2.5uA.
    06:43 Finally beam back. Returning to production runs.