• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name A. Camsonne

    Log entry time 16:03:07 on October19,2004

    Entry number 134726

    keyword=Day shift summary

    Day shift summary

    8:44 MCC has trouble delivering beam... beam away for a couple of minutes

    8:55 beam back


    10:33-10:48 Two arms runs

    10:52 back to production

    1:30 MCC called expert to look at some problems, estimate time needed is 15 minutes

    1:45 Beam came back shortly but it seems the problem is still there

    1:58 MCC called they need to repair something time estimate in 30 to 40 minutes, so starting LED calibration

    14:10 MCC called they said they could resume beam so going back to data taking settings

    14:12 start of run 3950

    14:20 Bleedthrough measurement 2.59%

    15:21 Dummy target 4 cm run

    15:37 Dummy target 15 cm run

    16:00 Run DVCS 3953 running... for the next shift

    Run list

    DVCS production
    Run Number: 3941 150k events
    BCM u10[0]:0.007913

    Run Number: 3942 150k events
    BCM u10[0]:0.008033

    Run Number: 3943 150k events
    BCM u10[0]:0.00798

    Run Number: 3946 150k event
    BCM u10[0]:0.007903

    Run Number: 3947 150k event
    BCM u10[0]:0.007999

    Run Number: 3948 38 k events
    BCM u10[0]:0.002034

    Run Number: 3949 short run ( no beam )

    Run Number: 3950 150k event
    BCM u10[0]:0.008101


    Two arms runs
    Run Number: 3944
    BCM u10[0]:0.0007092

    Optic run
    Run Number: 3945
    BCM u10[0]:0.0008098

    Dummy target runs
    Run number 3951 Dummy 4 cm

    Run number 3952 Dummy 15 cm