8:00 Beams stops for us.
HV from DVCS detector all off.
MCC starts beam studies
Spectrometers ramping down
8:55 MCC called and asked if they could use the raster since we are on empty target there is no problem with the raster.
11:00 Hall to controlled access to change kinematic
12:00 Start of UV lamp curing on block 121
Led runs taken before run 4002
14:41 Turned off curing lamp Run LED taken 4003
15:30 Beam into the hall
Compton tuning starts, tune looks pretty good
vertical scan