    Hall A

    10/25/04 0000-0800
    Experiment #: DVCS
    Shift Leader: C. Munoz Camacho
    Shift Workers: C. Ferdi

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.530.640.810.860.900.940.880.005.55
    Beam Available
    but Not in Use
    0.050.000.110.020.030.010.020.000.24
    Beam Not Available
    or Unacceptable
    0.420.360.080.120.070.050.111.002.20
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments:

    Data Entry by: C. Munoz Camacho