Hall A Experiment #: DVCS
11/03/04 1600-2400
Shift Leader: Eric Voutier
Shift Workers: Jean-Sebastien Real, Malek Mazouz
1600 | 1700 | 1800 | 1900 | 2000 | 2100 | 2200 | 2300 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0.82 | 0.84 | 0.76 | 0.75 | 0.90 | 0.87 | 0.93 | 0.34 | 6.21 |
Beam Available but Not in Use | 0.02 | 0.03 | 0.02 | 0.05 | 0.03 | 0.03 | 0.00 | 0.37 | 0.54 |
Beam Not Available or Unacceptable | 0.16 | 0.13 | 0.22 | 0.20 | 0.07 | 0.10 | 0.07 | 0.28 | 1.24 |
Accelerator Con- figuration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Experiment Ready | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 0.75 | 7.75 |
Planned Config- uration Change | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.25 | 0.25 |
Unplanned Experiment Down | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Hall not ready reasons | |||||||||
Target | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Data Acq | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Other | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSL | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HRSR | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
HALL_OFF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Comments: Poor beam at the end of the shift
Data Entry by: Eric Voutier